NTSB says bolts on Boeing jetliner were missing before a panel blew out in midflight last month
This photo released by the National Transportation Safety Board shows the door plug from Alaska Airlines Flight 1282 on Jan. 8, 2024, in Portland, Ore. Investigators say bolts that helped secure the panel on the Boeing jetliner were missing before the panel blew off the plane in midflight last month. The National Transportation Safety Board issued a preliminary report Tuesday, Feb. 6 into the Jan. 5 accident. The loss of the panel forced pilots of the Alaska Airlines Boeing 737 Max 9 jet to make a harrowing emergency landing. Credit: National Transportation Safety Board via AP, file

Bolts that helped secure a panel to the frame of a Boeing 737 Max 9 were missing before the panel blew off the Alaska Airlines plane last month, according to accident investigators.

The National Transportation Safety Board issued a preliminary report on the Jan. 5 incident Tuesday.

The report included a photo from Boeing, which worked on the panel, which is called a door plug. In the photo, three of the four bolts that prevent the panel from moving upward are missing. The location of the fourth bolt is obscured.

The investigators said that the lack of certain damage around the panel indicates that all four bolts were missing before the plane took off from Portland, Oregon.

Pilots were forced to make a harrowing emergency landing with a hole in the side of the .

Without the bolts, nothing prevented the panel from sliding upward and detaching from "stop pads" that secured it to the airframe.

The said the door plug, installed by supplier Spirit AeroSystems, arrived at Boeing's factory near Seattle with five damaged rivets around the plug. A Boeing crew replaced the damaged rivets, which required them to remove the four bolts to open the plug.

The Federal Aviation Administration is separately investigating whether Boeing and its suppliers followed proper safety procedures in manufacturing parts for the Max. The FAA has barred Boeing from speeding up production of 737s until the agency is satisfied about quality issues.

FAA Administrator Michael Whitaker said Tuesday that his agency is about halfway through a six-week audit of manufacturing processes at Boeing and its key supplier on the Max, Spirit AeroSystems. He said the agency is confronted with two questions—what's wrong with the Max 9, and "what's going on with the production at Boeing?"

© 2024 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed without permission.

Citation: NTSB says bolts on Boeing jetliner were missing before a panel blew out in midflight last month (2024, February 6) retrieved 6 February 2024 from https://techxplore.com/news/2024-02-ntsb-boeing-jetliner-panel-blew.html

This document is subject to copyright. Apart from any fair dealing for the purpose of private study or research, no part may be reproduced without the written permission. The content is provided for information purposes only.